EX-10.1
from 8-K 24 pages Cheniere Energy, Inc. $1,200,000,000 5.800% Senior Notes Due 2037 Registration Rights Agreement
12/34/56
EX-10.1
from 10-Q 6 pages Change Order Thermal Oxidizer Burner Retrofit Kits
12/34/56
EX-10.7
from 10-Q 457 pages Certain Information of This Document Has Been Redacted Because It Is Both (I) Not Material and (II) Would Likely Cause Competitive Harm if Publicly Disclosed. Information That Was Omitted Has Been Noted in This Document With a Placeholder Identified by the Mark “[***].” Lump Sum Turnkey Agreement for the Engineering, Procurement and Construction of the Sabine Pass LNG Stage 5 Liquefaction Project by and Between Sabine Pass Liquefaction Stage V, LLC as Owner and Bechtel Energy Inc. as Contractor Dated as of the 22 Day of May 2026
12/34/56
EX-10.1
from 10-Q 3 pages Change Order Acceleration Program Extension
12/34/56
EX-10.1
from 8-K 32 pages Commitment Increase and Maturity Extension Agreement
12/34/56
EX-10.1
from 10-Q 8 pages Change Order Stage 3 VI-Go Fall Arrest System
12/34/56
EX-10.1
from 8-K 3 pages Third Employment Agreement Amendment
12/34/56
EX-10.1
from 8-K 24 pages Cheniere Energy, Inc. $1,000,000,000 5.200% Senior Notes Due 2036 $750,000,000 6.000% Senior Notes Due 2056 Registration Rights Agreement
12/34/56
EX-10.46
from 10-K 5 pages Change Order P&ID Natives for Trains 3 Through 7 and Osbl Phase 2
12/34/56
EX-10.1
from 10-Q 11 pages Change Order Owner Accommodations at Contractor Citywest Offices
12/34/56
EX-10.1
from 10-Q 20 pages Change Order Hazop Provisional Sum Closure
12/34/56
EX-10.1
from 10-Q 2 pages Change Order #57 Crushed Rock for Surface Paving - Isbl Areas
12/34/56
EX-10.46
from 10-K 13 pages Change Order Local Temperature Indication at LNG Rundown Line
12/34/56
EX-10.2
from 10-Q 6 pages Change Order 30pk-3301a/B/C Firewater Pump Protection - Detailed Design and Partial Procurement of Blast Resistant Doors
12/34/56
EX-10.1
from 8-K 3 pages This Letter Agreement (“Letter Agreement”) When Executed by You Will Constitute the Agreement Between Cheniere Energy, Inc. (The “Company” or “Cheniere”) and John Corey Grindal (“Employee”), a Current Employee of Cheniere Energy Shared Services Inc. Company and Employee Are Referred to Collectively Hereafter as the “Parties” and Individually as “Party”. Employee Hereby Agrees to Remain Employed in a Full-Time Position, as Executive Vice President and Chief Operating Officer, Reporting to Jack Fusco Until October 2, 2024, at Which Time Employee Will Transition to Executive Vice President and Advisor, Reporting to Jack Fusco. Employee Understands That He Will Be Available as Needed for Business Needs as Directed by Jack Fusco, Employee Will Not Report to Company Locations for Work, and Will No Longer Have Access to Cheniere Systems After October 2, 2024. Employee Will Remain Employed by Cheniere Energy Shared Services Inc. Until January 2, 2025 (Separation Date), as an At-Will Employee, at Which Time Employee’s Employment Will End Upon His Severance Under the Key Executive Severance Pay Plan. Employee Agrees That Satisfactory Performance in Accordance With Employee’s Job Duties, as Specified in Writing, and Determined by the Company in Its Sole Reasonable Discretion, and Cheniere’s Policies Is Required Throughout This Period
12/34/56
EX-10.7
from 10-Q 4 pages First Amendment to Second A&R Working Capital Facility Agreement
12/34/56
EX-10.6
from 10-Q 11 pages First Amendment to Second A&R Common Security and Account Agreement
12/34/56
EX-10.5
from 10-Q 15 pages First Amendment to Second A&R Common Terms Agreement
12/34/56
EX-10.1
from 10-Q 9 pages Change Order CCL Tanks “A” and “C” Engineering, Procurement and Construction
12/34/56
EX-10.1
from 8-K 29 pages Cheniere Energy, Inc. Amended and Restated 2020 Incentive Plan
12/34/56